Fuel loading could begin at unit 3 as early as the first quarter of 2022, the company said, but a fuel load date as late as May 2022 "should support" a third-quarter 2022 in-service date. Vogtle 4's containment, on the left, and turbine building, on the right, pictured in September (Image: Georgia Power)ĭirect construction of unit 3 - where hot functional testing has already been completed - is now 99% complete, and the overall Vogtle 3 and 4 expansion project is about 95% complete. An in-service date in the third quarter of 2022 is now projected for Vogtle 3, with Vogtle 4's in-service date set for the second quarter of 2023. Georgia Power has shifted back by three months the schedule for the Vogtle 3 and 4 expansion project, citing the need for extra time to address construction challenges and to allow for comprehensive testing.